Measurement #4 01.07.2021

Experiment Log 2021

Thursday 01/07/2021 was the fourth data acquisition for PLP2021. This was the last acquisition with the 8 square targets built for the REACT project. The 8 targets were removed after Sentinel 2...

Read More →

Measurement #3 26.06.2021

Experiment Log 2021

Saturday 26/06/2021 was the third data acquisition for PLP2021. Sentinel 2 multispectral data of both the two large area targets (HDPE mesh and wooden plank/natural debris simulator) and the 8...

Read More →

Measurement #2 21.06.2021

Experiment Log 2021

Tuesday 21/06/2021 was the second acquisition day of PLP2021. Sentinel 2 data of the deployment area containing both the HDPE mesh and the natural debris targets were acquired. In addition to the 2...

Read More →

Target 2 Placement 17.06.2021

Experiment Log 2021

On Thursday 17/06/2021 we deployed the wooden 28 m target in the Gulf of Gera. A group of 3 MRSG team members, one Department of Marine Sciences student volunteer and a professional diver worked for...

Read More →

Bad Weather Conditions

Experiment Log 2021

Wednesday 16/06/2021 was scheduled for the second Sentinel 2 acquisition for PLP2021. Weather conditions were unideal, with dense cloud cover and rain not allowing for the acquisition of cloud free,...

Read More →

Target 2 Construction Day 1

Experiment Log 2021

On Tuesday 15/06/2021 we constructed a wooden target which simulates natural floating debris, in order to assess the possibility to discriminate between floating plastic litter and natural floating...

Read More →

Measurement #1 11.06.2021

Experiment Log 2021

Friday 11/06/2021 was the first acquisition day of PLP2021. Conditions were optimal with low wind and a slightly rippled sea surface. Sentinel 2 data were acquired over crystal clear skies. Drone...

Read More →

Target 1 Placement 09.06.2021

Experiment Log 2021

On Wednesday 09/06/2021 we carried out the deployment of the 28 m diameter HDPE mesh target. We commenced by inspecting the target for potential damage and made final adjustments and improvements to...

Read More →

Target 1 Construction Day 2

Experiment Log 2021

On Tuesday 08/06/2021 we resumed construction of the 28 m diameter circular long-term deployment target. A team of 20 MRSG members and University of the Aegean student volunteers worked on the...

Read More →

Target 1 Construction Day 1

Experiment Log 2021

Friday 04/06/2021 was the official start of the PLP2021 target construction phase. A group of 20 MRSG team members and volunteer students worked in Skala Loutron to assemble the HDPE mesh sheet that...

Read More →
↑